[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896643,581,1,"单选题","某混凝土构件采用木模板施工，木模板一次净用量为 200 ㎡，现场制作安装不可避免的损耗率为 2％，木模板可周转使用 5 次，每次补损率为 5％，则木模板的周转使用量为（）㎡。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","48.00",false,{"key":16,"text":17,"correct":18},"B","48.96",true,{"key":20,"text":21,"correct":14},"C","49.44",{"key":23,"text":24,"correct":14},"D","51.00","本题考查的是周转性材料消耗定额的编制。 一次使用量＝净用量×（1＋操作损耗率） 200×（1+2%）×[1+（5-1）×5%]\u002F5=48.96 ㎡",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]