[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896635,581,1,"单选题","施工机械工作时间中的不可避免的中断时间应属于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","有效工作时间",false,{"key":16,"text":17,"correct":14},"B","停工时间",{"key":19,"text":20,"correct":14},"C","不可避免的无负荷工作时间",{"key":22,"text":23,"correct":24},"D","定额时间",true,"不可避免的中断时间是与工艺过程的特点、机械使用中的保养、工人休息等有关的中断时间。如汽车装卸货物的停车时间，给机械加油的时间，工人休息时的停机时间。是必须消耗的时间，属于定额时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]