[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896634,581,1,"单选题","修磨校验工具、移动工作梯、工人转移工作地点等所需时间属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","辅助工作时间",true,{"key":16,"text":17,"correct":18},"B","由于施工工艺特点引起的工作中断时间",false,{"key":20,"text":21,"correct":18},"C","施工本身造成的停工时间",{"key":23,"text":24,"correct":18},"D","准备与结束工作时间","辅助工作时间是指为了保证基本工作顺利完成而同技术操作无直接关系的辅助性工作时间。如修磨校验工具、移动工作梯、工人转移工作地点等所需时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]