[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896631,581,1,"单选题","编制材料消耗定额的基本方法中，用（ ）主要是为了取得编制材料损耗定额的资料。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","统计法",false,{"key":16,"text":17,"correct":14},"B","试验法",{"key":19,"text":20,"correct":21},"C","现场技术测定法",true,{"key":23,"text":24,"correct":14},"D","理论计算法","现场技术测定法主要是为了取得编制材料损耗定额的资料。材料消耗中的净用量比较容易确定，但材料消耗中的损耗量不能随意确定，需通过现场技术测定来区分哪些属于难以避免的损耗，哪些属于可以避免的损耗，从而确定出较准确的材料损耗量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]