[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896625,581,1,"单选题","正常施工条件下，完成单位合格建筑产品所需某材料的不可避免损耗量为0．90kg，已知该材料的损耗率为7．20%，则其总消耗量为（ ）kg。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13．50",false,{"key":16,"text":17,"correct":18},"B","13．40",true,{"key":20,"text":21,"correct":14},"C","12．50",{"key":23,"text":24,"correct":14},"D","11．60","材料总消耗量=材料消耗净用量+材料损耗量； 材料损耗率=（材料损耗量\u002F材料净用量） x 100% (即:材料损耗量=材料净用量×损耗率) ； 材料净用量=0.9\u002F7.2%；总消耗量=0.9\u002F7.2%+0.9=13.4。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]