[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896623,581,1,"单选题","编制人工定额时，工人定额工作时间中应予以合理考虑的情况是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由于水源或电源终端引起的停工时间",true,{"key":16,"text":17,"correct":18},"B","由于工程技术人员和工人差错引起的工时损失",false,{"key":20,"text":21,"correct":18},"C","由于劳动组织不合理导致工作中断所占用的时间",{"key":23,"text":24,"correct":18},"D","由于材料供应不及时引起的停工时间","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]