[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896622,581,1,"单选题","概算定额的编制步骤不包括的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","准备工作阶段",false,{"key":16,"text":17,"correct":14},"B","编制初稿阶段",{"key":19,"text":20,"correct":21},"C","编制定额项目表",true,{"key":23,"text":24,"correct":14},"D","审查定稿阶段","概算定额的编制步骤： 1.准备工作阶段； 2.编制初稿阶段； 3.审查定稿阶段。 考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]