[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896619,581,1,"单选题","概算定额与预算定额的差异主要表现在（ ）的不同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目划分",true,{"key":16,"text":17,"correct":18},"B","主要工程内容",false,{"key":20,"text":21,"correct":18},"C","主要表达方式",{"key":23,"text":24,"correct":18},"D","基本使用方法","本题考查的是预算定额、概算定额、概算指标、投资估算指标和造价指标。预算定额是在正常的施工条件下，完成一定计量单位合格分项工程和结构构件所需消耗的人工、材料、施工机具台班数量及其费用标准。概算定额是完成单位合格扩大分项工程，或扩大结构构件所需消耗的人工、材料、施工机具台班的数量及其费用标准。综上，概算定额与预算定额的差异主要表现在项目划分的不同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]