[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896617,581,1,"单选题","下列用时中，同时包含在劳动定额和预算定额人工消耗量中的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程验收的影响时间",false,{"key":16,"text":17,"correct":14},"B","工序搭接发生的停歇时间",{"key":19,"text":20,"correct":21},"C","不可避免的中断时间",true,{"key":23,"text":24,"correct":14},"D","加工材料所需的时间","本题考查的是预算定额、概算定额、概算指标、投资估算指标和造价指标。运用排险法，辅助用工指施工现场发生的加工材料等的用工。如筛砂子、淋石灰膏的用工。人工幅度差主要指正常施工条件下，劳动定额中没有包含的用工因素。例如各工种交叉作业配合工作的停歇时间，工程质量检查和工程隐蔽、验收等所占的时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]