[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896616,581,1,"单选题","预算定额的施工机械台班消耗指标的计量单位是台班，按现行规定，每个工作台班按机械工作（ ）小时计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","8",true,{"key":23,"text":24,"correct":14},"D","12","预算定额的施工机械台班消耗指标的计量单位是台班。按现行规定，每个工作台班按机械工作8小时计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]