[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896602,581,1,"单选题","概算指标是以( )为对象的消耗指标。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程",false,{"key":16,"text":17,"correct":14},"B","分部工程",{"key":19,"text":20,"correct":21},"C","整个建筑物或构筑物",true,{"key":23,"text":24,"correct":14},"D","分项工程","概算指标是以整个建筑物或构筑物为对象，以“m2 ”、“m3”或\"座\"等为计量单位，规定了人工、材料、机具台班的消耗指标的一种标准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]