[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896601,581,1,"单选题","完成某单位分部(分项)工程需要基本用工4．2工日，超运距用工0．3工日，辅助用工1工日，人工幅度系数为10%，则该单位分部(分项)工作预算定额人工消耗量为（ ）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5．92",false,{"key":16,"text":17,"correct":14},"B","5．95",{"key":19,"text":20,"correct":14},"C","6．02",{"key":22,"text":23,"correct":24},"D","6．05",true,"人工消耗量=(1+10%)×(4.2+0.3+1)工日=6.05工日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]