[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896587,581,1,"单选题","工程定额计价法的第二阶段的工作内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","熟悉图纸和现场",true,{"key":16,"text":17,"correct":18},"B","套定额单价",false,{"key":20,"text":21,"correct":18},"C","计算工程量",{"key":23,"text":24,"correct":18},"D","收集资料","工程定额计价的程序： 1.第一阶段：收集资料 2.第二阶段：熟悉图纸和现场 3.第三阶段：计算工程量 4.第四阶段：套定额单价 5.第五阶段：编制工料分析表 6.第六阶段：费用计算 7.第七阶段：复核 8.第八阶段：编制说明",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]