[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896585,581,1,"单选题","工程造价计价的顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程项目单价→单项工程造价→单位工程造价→建设项目总造价",false,{"key":16,"text":17,"correct":18},"B","分部分项工程造价→单位工程造价→单项工程造价→建设项目总造价",true,{"key":20,"text":21,"correct":14},"C","单项工程造价→单位工程造价→工程项目单价→建设项目总造价",{"key":23,"text":24,"correct":14},"D","单位工程造价→单项工程造价→工程项目单价→建设项目总造价","工程计价的方法有多种，各有差异，但工程计价的基本过程和原理是相同的。从工程费用计算角度分析，工程计价的顺序是：分部分项工程造价→单位工程造价→单项工程造价→建设项目总造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]