[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896584,581,1,"单选题","在下列各种定额中，以工序为研究对象的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算定额",false,{"key":16,"text":17,"correct":18},"B","施工定额",true,{"key":20,"text":21,"correct":14},"C","预算定额",{"key":23,"text":24,"correct":14},"D","投资估算指标","施工定额是指完成一定计量单位的某一施工过程，或基本工序所需消耗的人工、材料和施工机具台班数量标准。施工定额是施工企业成本管理和工料计划的重要依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]