[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896573,581,1,"单选题","在建设工程项目总投资组成中的基本预备费主要是为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设期内材料价格上涨增加的费用",false,{"key":16,"text":17,"correct":14},"B","因施工质量不合格返工增加的费用",{"key":19,"text":20,"correct":21},"C","设计变更增加工程量的费用",true,{"key":23,"text":24,"correct":14},"D","因业主方拖欠工程款增加的承包商贷款利息","基本预备费又称不可预见费。主要指设计变更及施工过程中可能增加工程量的费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]