[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896529,581,1,"单选题","某项目购买一台国产设备，其购置费为2500万元，运杂费率为15%，则该设备的原价为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2165．89",false,{"key":16,"text":17,"correct":18},"B","2173．91",true,{"key":20,"text":21,"correct":14},"C","2265．38",{"key":23,"text":24,"correct":14},"D","2364．16","根据公式：设备购置费=设备原价+设备运杂费， 又因为：设备运杂费=设备原价×设备运杂费率 所以，设备原价=设备购置费\u002F（1+设备运杂费率），可得设备原价=2500万元\u002F（1+15%），得设备原价=2173.91万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]