[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896520,581,1,"单选题","某项目拟从国外进口一套设备，重1000吨，装运港船上交货价300万美元，国际运费标准每吨360美元，海上运输保险费率0.266%。美元银行外汇牌价6.1元人民币。则该套设备国外运输保险费为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4.868",false,{"key":16,"text":17,"correct":14},"B","4.881",{"key":19,"text":20,"correct":14},"C","5.452",{"key":22,"text":23,"correct":24},"D","5.467",true,"国外运输保险费=[（离岸价+国外运费）\u002F（1-国外运输保险费率）]×国外运输保险费率=（3000000+360×1000）÷（1-0.266％）×0.266％×6.1=54670元=5.467万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]