[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896505,581,1,"单选题","根据我国现行建筑安装工程费用项目组成的规定，下列费用中应计入暂列金额的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工过程中可能发生的工程变更以及索赔、现场签证等费用",true,{"key":16,"text":17,"correct":18},"B","应建设单位要求，完成建设项目之外的零星项目费用",false,{"key":20,"text":21,"correct":18},"C","对建设单位自行采购的材料进行保管所发生的费用",{"key":23,"text":24,"correct":18},"D","施工用电、用水的开办费","应计入暂列金额的是施工过程中可能发生的工程变更以及索赔、现场签证等费用，暂列金额是指建设单位在工程量清单中暂定并包括在工程合同价款中的一笔款项。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]