[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896467,581,1,"单选题","建设工程造价的最高限额是按照有关规定编制并经有关部门批准的（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初步投资估算",false,{"key":16,"text":17,"correct":14},"B","施工图预算",{"key":19,"text":20,"correct":14},"C","施工标底",{"key":22,"text":23,"correct":24},"D","设计概算",true,"初步设计是工程设计投资控制的最关键环节，经批准的设计概算是工程造价控制的最高限额，也是控制工程造价的主要依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]