[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896464":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896464,581,1,"单选题","工程施工阶段，以（ ）等为控制依据，通过控制工程变更、风险管理等方法，按照承包人实际完成的工程量，严格确定施工阶段实际发生的工程费用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程合同价",true,{"key":16,"text":17,"correct":18},"B","拟建项目的功能要求和使用要求",false,{"key":20,"text":21,"correct":18},"C","被批准的设计概算",{"key":23,"text":24,"correct":18},"D","工程设计文件","以工程合同价等为控制依据，通过控制工程变更、风险管理等方法，按照承包人实际应予计量的工程量 ，并考虑物价上涨、工程变更等因素，合理确定进度款和结算款，控制工程费用的支出。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]