[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896460":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896460,581,1,"单选题","推行限额设计时，初步设计阶段的直接控制目标是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经批准的投资估算",true,{"key":16,"text":17,"correct":18},"B","经批准的设计概算",false,{"key":20,"text":21,"correct":18},"C","经批准的施工图预算",{"key":23,"text":24,"correct":18},"D","经确定的工程合同价","运用设计标准与标准设计、价值工程和限额设计方法等，以可行性研究报告中被批准的投资估算为工程造价目标值，控制和修改初步设计以满足投资控制目标的要求。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]