[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896458":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896458,581,1,"单选题","为了有效地控制建设工程造价，造价工程师可采取的组织措施是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ａ.重视工程设计多方案的选择",false,{"key":16,"text":17,"correct":18},"B","Ｂ.明确造价控制者及其任务",true,{"key":20,"text":21,"correct":14},"C","Ｃ.严格审查施工组织设计",{"key":23,"text":24,"correct":14},"D","Ｄ.严格审核各项费用支出","技术与经济相结合是控制工程造价最有效的手段。要有效地控制工程造价，应从组织、技术、经济等多方面采取措施。从组织上采取的措施，包括明确项目组织结构，明确造价控制者及其任务，明确管理职能分工；从技术上采取措施，包括重视设计多方案选择，严格审查监督初步设计、技术设计、施工图设计、施工组织设计，深入技术领域研究节约投资的可能；从经济上采取措施，包括动态地比较造价的计划值和实际值，严格审核各项费用支出，采取对节约投资的有力奖励措施等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]