[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896450,581,1,"单选题","下列关于CM(Construction Management)模式的说法中，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","CM模式特别适用于实施周期长、工期要求紧迫的大型复杂工程项目",false,{"key":16,"text":17,"correct":14},"B","CM模式有利于控制工程质量和造价",{"key":19,"text":20,"correct":14},"C","CM承包模式使工程项目实现有条件的“边设计、边施工”",{"key":22,"text":23,"correct":24},"D","快速路径法施工并不适合CM承包模式",true,"CM (Construction Management)模式是指由建设单位委托一家CM单位承担项目管理工作，该CM单位以承包商身份进行施工管理，并在一定程度上影响工程设计活动，组织快速路径( Fast - Track)的生产方式，使工程项目实现有条件的\"边设计、边施工。CM模式特别适用于实施周期长、工期要求紧迫的大型复杂工程项目。采用CM模式，不仅有利于缩短工程项目建设周期，而且有利于控制工程质量和造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]