[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896447,581,1,"单选题","CM（ConstructionManagement）承包模式的特点是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位与分包单位直接签订合同",false,{"key":16,"text":17,"correct":14},"B","采用流水施工法施工",{"key":19,"text":20,"correct":14},"C","CM单位可赚取总分包之间的差价",{"key":22,"text":23,"correct":24},"D","采用快速路径法施工",true,"本题考查的是工程项目实施模式。CM（ConstructionManagement）模式是指由建设单位委托一家CM单位承担项目管理工作，该CM单位以承包商身份进行施工管理，并在一定程度上影响工程设计活动，组织快速路径（Fast-Track）的生产方式，使工程项目实现有条件的“边设计、边施工”。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]