[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896441,581,1,"单选题","以下（）PPP模式社会资本方承担的风险相对较小。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","私有化类",false,{"key":16,"text":17,"correct":14},"B","民营化类",{"key":19,"text":20,"correct":14},"C","特许经营类",{"key":22,"text":23,"correct":24},"D","外包类",true,"外包类PPP项目中政府出资并承担项目经营和收益风险，社会资本方通过政府付费实现收益，承担的风险相对较少。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]