[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896396,581,1,"单选题","施工安装活动应按照工程设计要求、施工合同条款、有关工程建设法律法规规范标准及施工组织设计，在保证工程质量、工期、成本及安全、环保等目标的前提下进行，达到竣工验收标准后，由（ ）移交给建设单位。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":14},"B","分包单位",{"key":19,"text":20,"correct":14},"C","设计单位",{"key":22,"text":23,"correct":24},"D","施工单位",true,"施工安装活动应按照工程设计要求、施工合同及施工组织设计，在保证工程质量、工期、成本及安全、环保等目标的前提下进行，达到竣工验收标准后，由施工单位移交给建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]