[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896390,581,1,"单选题","建设项目在开工建设之前要切实做好各项准备工作，其主要内容不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","征地、拆迁、场地平整以及基坑开挖工作",true,{"key":16,"text":17,"correct":18},"B","完成施工用水、电、通信、道路等接通工作",false,{"key":20,"text":21,"correct":18},"C","组织招标选择施工单位及设备、材料供应商",{"key":23,"text":24,"correct":18},"D","准备必要的施工图纸","建设准备工作内容。1）征地、拆迁和场地平整；2）完成施工用水、电、通信、道路等接通工作；3）组织招标选择工程监理单位、施工单位及设备、材料供应商；4）准备必要的施工图纸；5）办理工程质量监督和施工许可手续。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]