[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896388,581,1,"单选题","竣工验收的准备工作不包括（ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","整理技术资料",false,{"key":16,"text":17,"correct":14},"B","绘制竣工图",{"key":19,"text":20,"correct":14},"C","编制竣工决算",{"key":22,"text":23,"correct":24},"D","组织验收委员会",true,"",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]