[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896309":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896309,581,1,"单选题","根据相关规定，工程未经竣工验收，发包人擅自使用的，以（ ）为实际竣工日期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交竣工验收报告之日",false,{"key":16,"text":17,"correct":18},"B","转移占有工程之日",true,{"key":20,"text":21,"correct":14},"C","监理人组织竣工初验之日",{"key":23,"text":24,"correct":14},"D","发包人签发工程接收证书之日","本题考查的是最高人民法院司法解释有关要求。根据相关规定，工程未经竣工验收，发包人擅自使用的，以转移占有工程之日为实际竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]