[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896292,581,1,"单选题","某承诺文件超过要约规定时间1天到达要约人， 按照邮寄文件收函邮局戳记标明的时间， 受要约人是在要求的时间投邮， 由于邮局错递而延误了到达时间， 对此情况， 该承诺文件应（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因迟到而自然无效",false,{"key":16,"text":17,"correct":14},"B","必须经要约人发出接受通知后有效",{"key":19,"text":20,"correct":21},"C","必须经要约人发出拒绝通知后才无效",true,{"key":23,"text":24,"correct":14},"D","因非受要约人原因的迟到，要约人必须接受该承诺","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]