[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896201,581,1,"单选题","根据《招标投标法实施条例》 ， 对于采用两阶段招标的项目。投标人在第一阶段向招标人提交的文件是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不带报价的技术建议",true,{"key":16,"text":17,"correct":18},"B","带报价的技术建议",false,{"key":20,"text":21,"correct":18},"C","不带报价的技术方案",{"key":23,"text":24,"correct":18},"D","带报价的技术方案","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]