[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896172,581,1,"单选题","根据九部委《标准施工招标文件》，监理人对隐蔽工程重新检查，经经验证明工程质量符合合同要求的，发包人应补偿承包人（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期和费用",false,{"key":16,"text":17,"correct":18},"B","工期、费用和利润",true,{"key":20,"text":21,"correct":14},"C","费用和利润",{"key":23,"text":24,"correct":14},"D","工期和利润","本题考查的是索赔费用的计算。监理人对隐蔽工程重新检查，经检验证明工程质量符合合同要求的，发包人应补偿承包人工期、费用和利润。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]