[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896170,581,1,"单选题","某单价合同履行中，承包人提交了已完工程量报告，发包人认为需要到现场计量，并在计量前24小时通知了承包人，但承包人收到通知后没有派人参加。则关于发包人现场计量结果的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以发包人的计量核实结果为准",true,{"key":16,"text":17,"correct":18},"B","以承包人的计量核实结果为准",false,{"key":20,"text":21,"correct":18},"C","由监理工程师根据具体情况确定",{"key":23,"text":24,"correct":18},"D","双方的计量核实结果均无效","考点:单价合同的计量。发包人认为需要进行现场计量核实时，应在计量前24小时通知承包人，承包人应为计量提供便利条件并派人参加。双方均同意核实结果时，则双方应在上述记录上签字确认。承包人收到通知后不派人参加计量，视为认可发包人的计量核实结果。参见教材P82。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]