[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896169,581,1,"单选题","某基础工程包含土方和混凝土两个子项工程，工程量清单中的土方工程量为4400m3，混凝土工程量为2000m3，合同约定土石方工程综合单价为75 元\u002Fm3，混凝土工程综合单价为420 元／m3；工程预付款额度为合同价的15%，主要材料和构配件所占比重为60%。则该工程预付款的额度及起扣点分别为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","17.55,87.75",true,{"key":16,"text":17,"correct":18},"B","17.10,99.45",false,{"key":20,"text":21,"correct":18},"C","17.10,87.75",{"key":23,"text":24,"correct":18},"D","17.55,99.45","合同总额P=4400×75＋2000×420=117 万元工程预付款额度=117×15%=17.55 万元起扣点T=P-M／N=117-117×15%÷60%＝87.75 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]