[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896167,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500&mdash;2013），如果因发包人原因删减了合同中原定的某项工作，致使承包人发生的费用或（和）得到的收益不能被包括在其他已支付的项目中，也未被包含在任何可替代的工作中，则承包人（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A．只能提出费用补偿，不能提出利润补偿",false,{"key":16,"text":17,"correct":14},"B","B．只能提出利润补偿，不能提出费用补偿",{"key":19,"text":20,"correct":21},"C","有权提出费用及利润补偿",true,{"key":23,"text":24,"correct":14},"D","无权要求任何费用和利润补偿","发包人的原因引起的工作内容增减，承包人有权提出得到合理的费用及利润补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]