[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896166,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500&mdash;2013），关于暂列金额的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．已签约合同中的暂列金额应由发包人掌握使用",true,{"key":16,"text":17,"correct":18},"B","B．已签约合同中的暂列金额应由承包人掌握使用",false,{"key":20,"text":21,"correct":18},"C","发包人按照合同规定将暂列金额作出支付后，剩余金额归承包人所有",{"key":23,"text":24,"correct":18},"D","发包人按照合同规定将暂列金额作出支付后，剩余金额由发包人和承包人共同所有","暂列金额并非是确定的工程内容，但是发包人担心发生，所以做了一些准备，是准备金的性质，因为不一定发生，所以自然由发包人掌握使用，工程竣工后如有剩余，余额归发包人所有。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]