[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896165":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896165,581,1,"单选题","关于总价合同计量的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．采用经审定批准的施工图纸及其预算方式发包形式的总价合同，其各项目的工程量是承包人用于结算的最终工程量",true,{"key":16,"text":17,"correct":18},"B","B．采用工程量清单方式招标形成的总价合同，其工程量必须以承包人实际完成的工程量确定",false,{"key":20,"text":21,"correct":18},"C","承包人不需要在每个计量周期向发包人提交已完成工程量报告",{"key":23,"text":24,"correct":18},"D","发包人应在收到工程量计量报告后14 天内进行复核","选项B，工程量清单方式招标形成的总价合同，工程量的计量参照单价合同的计量规定；选项C承包人应在每个计量周期向发包人提交已完工程量报告；选项D 发包人应在收到报告后的7 天内对承包人提交的上述资料进行复核。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]