[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896163,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500&mdash;2013），单价合同和总价合同两种合同形式均可采用工程量清单计价，其主要区别在于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A．采用单价合同时，工程量清单中所填写的工程量不可调整",false,{"key":16,"text":17,"correct":14},"B","B．采用总价合同时，工程量清单中所填写的工程量可调整",{"key":19,"text":20,"correct":14},"C","采用固定单价合同时，工程量清单项目综合单价在约定条件内可调整",{"key":22,"text":23,"correct":24},"D","采用固定单价合同时，工程量清单项目综合单价在约定条件内不可调整",true,"选项A，采用单价合同，工程量有约束力，可以调整；选项B，采用总价合同工程量无约束力，不可调；选项C 和选项D 说法相反，采用固定单价合同，在风险范围内是固定的，不可调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]