[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896139,581,1,"单选题","承包商可以向业主提起索赔的情形的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包商为确保质量而增加的措施费",false,{"key":16,"text":17,"correct":18},"B","监理工程师提出的工程变更造成费用的增加",true,{"key":20,"text":21,"correct":14},"C","分包商因返工造成费用增加，工期顺延",{"key":23,"text":24,"correct":14},"D","承包商自行采购材料的质量有问题造成费用增加、工期顺延","考点:索赔成立的条件。承包商可以提起索赔的事件包括：因工程变更（含设计变更、发包人提出的工程变更、监理工程师提出的工程变更，以及承包人提出并经监理工程师批准的变更）造成的时间、费用损失。参见教材P265。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]