[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896138,581,1,"单选题","工程施工过程中索赔事件发生以后，承包人首先要做的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．向监理工程师提出索赔意向通知",true,{"key":16,"text":17,"correct":18},"B","向监理工程师提交索赔依据",false,{"key":20,"text":21,"correct":18},"C","向监理工程师提交索赔报告",{"key":23,"text":24,"correct":18},"D","与业主就索赔事项进行谈判","本题考查的是索略意向通知和索赔通知发生索赔事件以后，或者承包人发现索赔机会，首先要提出索赔意向。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]