[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896135,581,1,"单选题","某住宅小区在施工过程中，开发商突然要求施工承包单位取消建设一处配套设备用房，施工承包单位在规定期限内向开发商提交了索赔报告，开发商未及时支付变更工程款也末提供替代工程，造成施工承包单位费用及利润损失，则费用及利润损失由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开发商",true,{"key":16,"text":17,"correct":18},"B","施工承包单位",false,{"key":20,"text":21,"correct":18},"C","双方共同承担",{"key":23,"text":24,"correct":18},"D","其他方式","因非承包人原因删减了合同中的某项原定工作或工程，致使承包人发生的费用或（和）得到的利益不能被包括在其他已支付或应支付的项目中，也未被包含在任何替代的工作或工程中，则承包人有权提出并得到合理的费用及利润补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]