[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896134,581,1,"单选题","某混凝土工程招标清单工程量为200m3，综合单价为300 元\u002Fm3。在施工过程中，由于工程变更导致实际完成工程量为250m3。合同约定当实际工程量增加超过15%时可调整单价，调价系数为0.9。该混凝土工程的实际工程费用为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6.00",false,{"key":16,"text":17,"correct":18},"B","7.44",true,{"key":20,"text":21,"correct":14},"C","7.50",{"key":23,"text":24,"correct":14},"D","8.25","由于混凝土工程实际工程量超过了工程量清单的工程数量15%，其超出部分的工程量为250-200×（1 十15%）=20m3，该部分的综合单价需要调整，故该混凝土工程的价款为200×（1+15%)×300+20×300×0.9=7.44 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]