[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896133,581,1,"单选题","某工程项目采用经审定批准的施工图纸及其预算方式分包形成的总价合同，在施工过程中进行某分项工程计量时发现，因工程变更，承包人实际完成的工程量超过了合同中的工程量，则进行该分项工程计量时应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．按照合同中的工程量计算",false,{"key":16,"text":17,"correct":18},"B","按变更后的工程量计算",true,{"key":20,"text":21,"correct":14},"C","按承包人提交的已完工程量计算",{"key":23,"text":24,"correct":14},"D","按发包人核准的工程量计算","采用经审定批准的施工图纸及其预算方式发包形成的总价合同，除按照工程变更规定引起的工程量增减外，总价合同各项目的工程量是承包人用于结算的最终工程量。因此，该分项工程计量应按变更后的工程量计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]