[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896129,581,1,"单选题","某工程基坑开挖恰逢雨季，造成承包商雨季施工增加费用超支，产生此费用偏差的原因是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主原因",false,{"key":16,"text":17,"correct":14},"B","设计原因",{"key":19,"text":20,"correct":21},"C","客观原因",true,{"key":23,"text":24,"correct":14},"D","施工原因","考点:赢得值（挣值）法。参见教材P120。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]