[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896127,581,1,"单选题","关于建设工程项目总进度目标的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设工程项目总进度目标的控制是施工总承包方项目管理的任务",false,{"key":16,"text":17,"correct":14},"B","项目实施阶段的总进度指的就是施工进度",{"key":19,"text":20,"correct":21},"C","在进行项目总进度目标控制前，应分析和论证目标实现的可能性",true,{"key":23,"text":24,"correct":14},"D","项目总进度目标论证就是要编制项目的总进度计划","考点:建设工程项目的总进度目标的内涵。在进行建设工程项目总进度目标控制前，首先应分析和论证目标实现的可能性。参见教材P126。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]