[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896126,581,1,"单选题","对某综合楼项目实施阶段的总进度目标进行控制的主体是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","建设单位",true,"考点:建设工程项目的总进度目标的内涵。建设工程项目总进度目标的控制是业主方项目管理的任务。参见教材P126。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]