[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896124,581,1,"单选题","关于用时间—成本累计曲线编制成本计划的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可调整非关键工作的开工时间以控制实际成本支出",true,{"key":16,"text":17,"correct":18},"B","全部工作必须按照最早开始时间安排",false,{"key":20,"text":21,"correct":18},"C","全部工作必须按照最迟开始时间安排",{"key":23,"text":24,"correct":18},"D","可缩短关键工作的持续时间以降低成本","考点:施工成本计划的编制方法。项目经理可根据编制的成本支出计划来合理安排资金，同时项目经理也可以根据筹措的资金来调整S形曲线，即通过调整非关键路线上的工序项目的最早或最迟开工时间，力争将实际的成本支出控制在计划的范围内。参见教材P112。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]