[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896121,581,1,"单选题","关于分部分项工程成本分析的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．施工项目成本分析是分部分项工程成本分析的基础",false,{"key":16,"text":17,"correct":18},"B","B．分部分项工程成本分析的对象是已完成分部分项工程",true,{"key":20,"text":21,"correct":14},"C","分部分项工程成本分析的资料来源是施工预算",{"key":23,"text":24,"correct":14},"D","分部分项工程成本分析的方法是进行预算成本与实际成本的&ldquo;两算&rdquo;对比","本题考核成本综合分析的内容。A 选项说反了。B 是对的，C 中分析资料来源包括很多；D 选项中，应该是预算成本、目标成本和实际成本的&ldquo;三算&rdquo;对比。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]