[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896119,581,1,"单选题","某工程主体结构混凝土工程量约3200m3，预算单价550 元\u002Fm3，计划4 个月内均衡完成。开工后，混凝土实际采购价格为560 元\u002Fm3。施工至第二个月底，实际完成混凝土工程量l800m3。运用赢得值法，可分析得到该工程发生了费用偏差，此时应采取的可行的纠偏措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．加快施工进度",false,{"key":16,"text":17,"correct":18},"B","重新选择混凝土供应商",true,{"key":20,"text":21,"correct":14},"C","调整工程数量",{"key":23,"text":24,"correct":14},"D","进行材料代用","因费用偏差CV=BCWP-ACWP＝990000-1008000＝-18000 元，项目费用超支。从题意可知，主要原因是混凝土实际采购价格高于预算单价，故可以通过重新选择混凝土供应商，寻求较低的实际采购价格，作为纠偏的可行措施。从上题可知，进度偏差SV 大于零，再加快施工进度对降低成本无助；调整工程数量和进行材料代用与设计不符，不能采用。所以，选项A、C、D 不恰当。选项B 合理，故选B。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]